Primary 220 kV Voltage Applied at Navoi TPP Substation
Primary 220 kV voltage was applied for the first time at the new substation of Navoi Thermal Power Plant. Through it, the plant and the 'Hybrid' solar power station were connected to the energy system.

Primary voltage was applied to the 220 kV busbars of the new 500/220 kV substation, the Ministry of Energy of Uzbekistan reported. The facility is being constructed as part of the project for the third combined-cycle gas turbine unit with a capacity of 650 MW at Navoi TPP.
Following the voltage application, the plant and the 300 MW 'Hybrid' solar photovoltaic power station were connected via the new substation. It is intended to strengthen electrical connections between the southwestern and northern parts of Uzbekistan's unified energy system, as well as enhance the reliability of electricity transmission across high-voltage networks.
The facility is installing equipment produced in Japan, China, India, and South Korea. The general contractor is a consortium of Mitsubishi Corporation and Mitsubishi Power Ltd.; Turkish Çalik Enerji is involved as a subcontractor.
The next stage involves applying voltage to the equipment for transmitting electricity from the new combined-cycle gas turbine unit to the country's unified energy system. Following this, final tests and inspections will be conducted, and the unit will be commissioned in stages.